Progress of Channel Construction on Jl. Ksatriaan 8 Kebon Manggis Reaches 70 Percent

Construction of 729-meter water channel located in Komplek TNI AD, on Jl. Ksatriaan 8 RW 03, Kebon Manggis, Matraman, East Jakarta has touched 70 percent.

Currently, the work progress has reached around 70 percent and targeted to be completed in November

East Jakarta SDA Sub-agency's Drainage Development and Construction Section Head, Tengku Saugi Zikri stated, his side deployed one mini backhoe to accelerate the construction work.

"Total length of this channel is 729 meters. Currently, the work progress has reached around 70 percent and targeted to be completed in November," he explained, Friday (10/1).

Starting October 3, Traffic Engineering on Jl. I Gusti Ngurah Rai will Be Implemented

According to him, this water channel will use U-ditch concrete with size 60x60 centimeters, 80x80 centimeters, and box culvert with size 80x80 centimeters.

The construction work was started from in front of church to Ksatriaan connecting (Phb) channel.

"We hope this construction work can be completed on schedule, which is 75 days," he closed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1717 personAldi Geri Lumban Tobing
  2. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1132 personDessy Suciati
  3. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye824 personDessy Suciati
  4. North Jakarta KPKP is Intensively Monitoring Animal Health Service Licensing

    access_time16-07-2026 remove_red_eye784 personAnita Karyati
  5. SDN Srengseng Sawah 15 Continues Face-to-Face Learning

    access_time13-07-2026 remove_red_eye713 personDessy Suciati