Pembangunan Saluran Air di Jl Ksatriaan 8 Kebon Manggis Capai 70 Persen
....
photo Nurito - Beritajakarta.id

Progress of Channel Construction on Jl. Ksatriaan 8 Kebon Manggis Reaches 70 Percent

Construction of 729-meter water channel located in Komplek TNI AD, on Jl. Ksatriaan 8 RW 03, Kebon Manggis, Matraman, East Jakarta has touched 70 percent.

Currently, the work progress has reached around 70 percent and targeted to be completed in November

East Jakarta SDA Sub-agency's Drainage Development and Construction Section Head, Tengku Saugi Zikri stated, his side deployed one mini backhoe to accelerate the construction work.

"Total length of this channel is 729 meters. Currently, the work progress has reached around 70 percent and targeted to be completed in November," he explained, Friday (10/1).

Starting October 3, Traffic Engineering on Jl. I Gusti Ngurah Rai will Be Implemented

According to him, this water channel will use U-ditch concrete with size 60x60 centimeters, 80x80 centimeters, and box culvert with size 80x80 centimeters.

The construction work was started from in front of church to Ksatriaan connecting (Phb) channel.

"We hope this construction work can be completed on schedule, which is 75 days," he closed.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1065 personAldi Geri Lumban Tobing
  2. Parekraf Agency Introduces Jakarta as a Global City at IBTM World 2024

    access_time23-11-2024 remove_red_eye938 personAldi Geri Lumban Tobing
  3. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye928 personFolmer
  4. Jakarta Baznas Bazis Ready to Support Disaster Preparedness

    access_time25-11-2024 remove_red_eye766 personAldi Geri Lumban Tobing
  5. Gubernatorial Election Logistics in Seribu Island Distributed

    access_time26-11-2024 remove_red_eye590 personBudhi Firmansyah Surapati