Pembangunan Saluran Air di Jl Ksatriaan 8 Kebon Manggis Capai 70 Persen

Progress of Channel Construction on Jl. Ksatriaan 8 Kebon Manggis Reaches 70 Percent

Construction of 729-meter water channel located in Komplek TNI AD, on Jl. Ksatriaan 8 RW 03, Kebon Manggis, Matraman, East Jakarta has touched 70 percent.

Currently, the work progress has reached around 70 percent and targeted to be completed in November

East Jakarta SDA Sub-agency's Drainage Development and Construction Section Head, Tengku Saugi Zikri stated, his side deployed one mini backhoe to accelerate the construction work.

"Total length of this channel is 729 meters. Currently, the work progress has reached around 70 percent and targeted to be completed in November," he explained, Friday (10/1).

Starting October 3, Traffic Engineering on Jl. I Gusti Ngurah Rai will Be Implemented

According to him, this water channel will use U-ditch concrete with size 60x60 centimeters, 80x80 centimeters, and box culvert with size 80x80 centimeters.

The construction work was started from in front of church to Ksatriaan connecting (Phb) channel.

"We hope this construction work can be completed on schedule, which is 75 days," he closed.

Linked News
Popular News indeks
  1. Low Emission Zones: Jakarta’s Concrete Step to Curb Air Pollution

    access_time13-04-2026 remove_red_eye1100 personAldi Geri Lumban Tobing
  2. Pademangan Health Center Promotes 3M Plus to Prevent Dengue Fever

    access_time14-04-2026 remove_red_eye815 personAnita Karyati
  3. Jakarta Provincial Government Fully Supports BTN JAKIM 2026

    access_time14-04-2026 remove_red_eye727 personDessy Suciati
  4. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye690 personFakhrizal Fakhri
  5. Jakarta Regional Budget Spending Reaches Rp10.38 Trillion in Q1

    access_time17-04-2026 remove_red_eye637 personDessy Suciati