Pembangunan Saluran Air di Jl Ksatriaan 8 Kebon Manggis Capai 70 Persen

Progress of Channel Construction on Jl. Ksatriaan 8 Kebon Manggis Reaches 70 Percent

Construction of 729-meter water channel located in Komplek TNI AD, on Jl. Ksatriaan 8 RW 03, Kebon Manggis, Matraman, East Jakarta has touched 70 percent.

Currently, the work progress has reached around 70 percent and targeted to be completed in November

East Jakarta SDA Sub-agency's Drainage Development and Construction Section Head, Tengku Saugi Zikri stated, his side deployed one mini backhoe to accelerate the construction work.

"Total length of this channel is 729 meters. Currently, the work progress has reached around 70 percent and targeted to be completed in November," he explained, Friday (10/1).

Starting October 3, Traffic Engineering on Jl. I Gusti Ngurah Rai will Be Implemented

According to him, this water channel will use U-ditch concrete with size 60x60 centimeters, 80x80 centimeters, and box culvert with size 80x80 centimeters.

The construction work was started from in front of church to Ksatriaan connecting (Phb) channel.

"We hope this construction work can be completed on schedule, which is 75 days," he closed.

Linked News
Popular News indeks
  1. JRF, Ye Concert Inject Rp 625 Billion into Jakarta's Economy

    access_time26-10-2026 remove_red_eye540 personDessy Suciati
  2. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye518 personAldi Geri Lumban Tobing
  3. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye505 personFolmer
  4. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye503 personAldi Geri Lumban Tobing
  5. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye500 personNurito